The vanity benchtops weren't delivered with the rest of the cabinetry, so there is a delay getting those installed.
Front brickwork
South side
Rear
North
Ensuite
Bathroom
Laundry
And the kitchen carcass which has since been installed:
Was also advised by the admin team that our caesarstone choice of "Mangrove" has been discontinued (why do we find these things out NOW?), so we had to choose from "Cashmere" or "Wild Rice". We've gone for Wild Rice so as to differentiate from the tiles, and hopefully hide a bit more grime!Apparently the tiler will be onsite at the end of this week, and due to finish early/mid next week. From late next week, the fitoffs are due to get underway, including the fitting/installation of basins, tapware, toilets, light points, switches, powerpoints, door handles, shelving, etc. These run over approximately a fortnight and is then followed by the installation of the carpet.
Almost looking like a home now! So much so that I have started the arduous task of packing up our rental now.