We have been invoiced for our frame stage!
The boys were good enough to help us out with some extra studs on the walls where we intend to wall-mount the TVs. Very useful!
We had a day delay on Wednesday on account of the gale-force winds, but they were still able to complete the frame on schedule so didn't 'claim' the delay. Otherwise a very straightforward week, so here are some pics:
When inspecting the site today we did find some minor issues with the framework, which we will ensure are rectified:
Admin have advised us that if the weather plays kind in Week 5, we should have a roof, fascia and gutters.
3 invoices down, 3 to go!
Glad that every week you have some new progress on your land... Soon your house will look more like a castle... ^.^
ReplyDelete